Proactive and Reactive Constraint Programming for Stochastic Project Scheduling with Maximal Time-Lags

Kim van den Houten, Léon Planken, Esteban Freydell, David M. J. Tax, Mathijs de Weerdt

제출 2024-09-13

원문 초록

This study investigates scheduling strategies for the stochastic resource-constrained project scheduling problem with maximal time lags (SRCPSP/max)). Recent advances in Constraint Programming (CP) and Temporal Networks have reinvoked interest in evaluating the advantages and drawbacks of various proactive and reactive scheduling methods. First, we present a new, CP-based fully proactive method. Second, we show how a reactive approach can be constructed using an online rescheduling procedure. A third contribution is based on partial order schedules and uses Simple Temporal Networks with Uncertainty (STNUs). Our statistical analysis shows that the STNU-based algorithm performs best in terms of solution quality, while also showing good relative offline and online computation time.

함께 살펴볼 논문

공통 태그를 근거로 연결했습니다. 실제 인용 관계나 논문의 우수성을 뜻하지 않습니다.

토론

이 논문과 연결된 포럼 글이 아직 없습니다.